Commissioners Court
Meeting Date: 06/04/2018  
FYI - Change Order No. 1 - Collin County Adventure Camp Trail Rehabilitation - Denco Construction Specialists
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for change order No. 1 to Denco Construction Specialists, IFB No. 2017-273, Collin County Adventure Camp Trail Rehabilitation. This change order is to change the gravel to a 50/50 mix of 3/8” minus crushed concrete, to 3/8” with fine crushed concrete. This blend matches the sample approved by the YMCA and Collin County. This blend will be used for the top cap of each trail type and will better meet both the durability and compaction needed for this type of project.
This change order totals $0.00
Total change orders for the project - $0.00 or 0.00%
 
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 1 to Denco CS Corp. for IFB 2017-273, Construction, Collin County Adventure Camp Trail Rehabilitation to change the gravel to a 50/50 mix of 3/8" minus crushed concrete and 3/8" with fine crushed concrete for the top cap of each trail type. jdg
HR and/or IT Action
Budget Department Action
Change Order No. 1 to Denco CS Corp for bid 2017-273, Construction, Collin County Adventure Camp Trail Rehabilitation.  No budget impact.  Bond Fund (405).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 1 to Construction, Collin County Adventure Camp Trail Rehabilitation (IFB No. 2017-273) with Denco CS Corp. to change the gravel to a 50/50 mix of 3/8" minus crushed concrete and 3/8" with fine crushed concrete for the top cap of each trail type, Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 0
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: 405-4121-561.91-01 / 01OC
Fund Transfers
Remarks:
 This change order totals $0.00
Attachments
memo
Contractor Proposal
Change Order 1