TxDOT request for Additional ROW funds: SH78 from Business 78 to FM6
Submitted By: Teresa Nelson
Department: Engineering  
Request Type: CONSENT Agenda Area: Budget Adj/Amend

Information
Department Action
On April 18, 2011, via Commissioners Court, CO#2011-241-04-18, approved an Agreement to Contribute Funds – Local Government with the Texas Department of Transportation (TxDOT) for 10% Right of Way participation on SH78 at Business 78 to FM6 (bond project 07-0011). This project was then and is now totally in the City of Lavon. However, TxDOT had the practice in 2011 of sending requests for ROW participation in small cities to the County. And the County had the practice of paying all of the participation even if part or all of the project was in a small city. The amount estimated for ROW in 2011 was $395,000; therefore, since the local government’s share is 10%, the County paid $39,500. After that payment the County was able to determine that the Grand Heritage Municipal Utility District in the City of Lavon had funding available, so the County was reimbursed the $39,500.

Per the attached letter, Texas Department of Transportation has completed the right of way acquisition and utilities, but the final total is $512,858.02. Therefore, the County’s share, per the signed agreement, is $51,285.80, and a balance of $11,785.80 is currently due. The bond account 07-0011 remains open with a balance of $0. The budget adjustment below will reallocate funds from FM1378 ROW project.

We seek Commissioners Court approval of the following budget adjustment to pay the remaining balance:

From: 070052 FM1378: FM1378N – FM3286
440-7530-680-9682 / 070052 $11,786

To: 070011 ROW wTxDOT-Hwy78frmBSH78
440-7530-680-9682 / 070011 $11,786


 
Purchasing Department Action
No action by Purchasing, budget amendment only. md
HR and/or IT Action
Budget Department Action
Budgeted funds available for the Budget Adjustment totaling $11,786 for the County's remaining portion of the 10% right of wayparticipation with TxDOT on SH78 at Business 78 to FM6. Bond Fund (440).
Auditor's Office Action
Tax note funds available.
Commissioners Court
Budget amendment in the amount of $11,786 to pay the Texas Department of Transportation (TxDOT) the remaining balance of the County’s 10% Right of Way participation on SH78 at Business 78 to FM6, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $11,786
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: 440-7530-680.96-82 / 070011
Fund Transfers
Trans Amt: $11,786 From: 440-7530-680.96-82 / 070052 To: 440-7530-680.96-82 / 070011
Dept. Name: Additional Line Items:
Remarks:
 
Remarks:
FY 2018 Budget Adjustment Totaling $11,786.