AI- 55728
Commissioners Court
Meeting Date: 04/01/2024  
Change Order No. 23 to Ratcliff Constructors for Construction, Collin County Adult Detention Facility
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners Court for contract Change Order No. 23 to Ratliff Constructors for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1.
PCO 87 – Owner requested change to add lighting to a mechanical chase.  The bid drawings showed no lighting.   $3,729.38
PCO 90 – Owner requested bond beam to lower a cased opening to match an area where we lowered the ceiling. $1,330.48
PCO 91 – Owner requested credit to reimburse for work not needed where the new hallway intersects the existing building.  The credit covers some fire alarm programming and reused doors. ($3,298.00)
PCO 92 – Engineer requested add to change 8 - X3 lights to sealed exterior lights, material only.  We will take the existing lights into stock for reuse. $4,306.32
PCO 93 – Owner requested add to install 12 data drops for WIFI points to connect the inmate phone system.  $6,382.89
Total for this change order – $12,451.07 or 0.03% of contract
Total changes for this contract – $932,052.25 or 2.43% of contract
 
Purchasing Department Action
FYI Notification to Commissioners Court of Contract Change Order No. 23 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 PCO 87, 90-93 Addition per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. cur 
 
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $12,451.07 for Change Order No. 23 to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition with Ratliff Constructors. New contract total is $39,192,052.25. 2007 Bond Fund (4020).
Auditor's Office Action
2007 Bond funds available (4020).
Commissioners Court
Change Order No. 23 to Construction, Collin County Adult Detention Facility, Phase 1 (IFB No. 2021-239) with Ratcliff Constructors, L.P. to provide various changes to the contract, Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $12,451.07
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI07JAIL-4020-400308002-809101
Fund Transfers
Remarks:
Attachments
Memo
Change Order No. 23
PCO 87
PCO 90
PCO 91
PCO 92
PCO 93