AI- 55741
Commissioners Court
Meeting Date:
04/15/2024
FYI Change Order #1: 2022-292 Construction: Building Automation Upgrade, Heat Transfer Solutions, Purchase Order 24001271
Submitted For:
Rick Monk
Submitted By:
Katie Elder
Department:
Facilities
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI for Purchase Order 24001271, change order #1 for modifying the sequence of operation to alternate chilled water pump leads on a weekly basis as recommended by Heat Transfer Solutions and supported by MD Engineering. The amount for change order # 1 is $7,550 making the purchase order amount $130,483.70.
Purchasing Department Action
FYI notification to Commissioners Court of contract Change Order No. 1 to Heat Transfer Solutions, Inc. for IFB No. 2022-292 Construction: Building Automation System Upgrades per the attached documents. This change order was previously approved by the County Administrator per Court Order 2007-180-02-27. (ha)
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $7,550 for Change Order No. 1 to Contract No. 2022-292 Construction: Building Automation System Upgrades to Heat Transfer Solution, Inc. (0499) – Permanent Improvement Fund.
Auditor's Office Action
Funds available in the Permanent Improvement Fund (0499).
Commissioners Court
Change Order No. 1 to Construction: Building automation System Upgrades (IFB No. 2022-292) with Heat Transfer Solutions, Inc. to add line items to the contract in the amount of $7,550, Facilities.
Budget Information
Information about available funds
Budgeted:
Funds Available:
Adjustment:
Amount Available:
7,550
Unbudgeted:
Funds NOT Available:
Amendment:
Account Code(s) for Available Funds
1:
BDJ4001-0499-400108016-809101
Fund Transfers
Remarks:
Attachments
MEMO
MD Memo
Change Order No. 1
HTS Proposal