AI- 55830
Commissioners Court
Meeting Date: 04/22/2024  
Change Order No. 25, Ratcliff Constructors, Construction, Collin County Adult Detention Facility, Phase 1 Addition
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners Court for contract Change Order No. to Ratliff Constructors for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1.
PCO 94 - Engineer required add for conduit and circuits to 59 additional file dampers. Circuitry not shown in the bid documents. $38,003.00 plus 5 days added to the schedule.  
PCO 96 - State code required lighting in the elevator pit. Added due to inspection. 
$4,749.32 
PCO 98 - Engineer requested individual regulators for boiler gas service. Field installers reported better service with the individual regulators as opposed to the one large regulator shown in the documents. $4,719.16 
New completion date, 5/27/24.
Total for this change order - $47,471.48 or 0.12% of contract 
Total changes for this contract- $1,036,643.26 or 2.71% of contract 
 
Purchasing Department Action
FYI Notification to Commissioners Court of Contract Change Order No. 25 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 PCO 94, 96, & 98 and to extend the completion date five(5) additional days to 5/27/2024. Addition per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. cur 
 
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $47,471.48 for Change Order No. 25 to IFB 22021-239, Construction, Collin County Adult Detention Facility, Phase 1 with Ratliff Constructors, L.P. New contract total is $39,296,643.26. 2007 Bond Fund (4020).
Auditor's Office Action
2007 Bond Funds (4020) available.
Commissioners Court
Change Order No. 25 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to make various changes to the contract, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $47,471.48
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI07JAIL-4020-400308002-809101
Fund Transfers
Attachments
Memo
Change Order 25
PCO 94
PCO 96
PCO 98