Contract Amendment No 4 (2015-107) with Jacobs Eng for Outer Loop East Bound Frontage Road
Submitted For: Jeff Durham Submitted By: Teresa Nelson
Department: Special Projects  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
 The Engineering Department requests that the contract with Jacobs Engineering for services relating to the CCOL westerly (south bound) service road be increased by $775,800.38.
 
The bulk ($560,688.50) of this increase is for construction phase services, including direct expenses, to provide part time project construction inspection. The balance ($215,111.88) being for additional engineering construction administrative services in support of construction activities.
 
Jacobs scope of work and a detailed breakdown of their proposed fees is attached.
 
Commissioners Courts approval of this contract amendment is requested and I will be available to answer any questions you might have regarding this matter.
 
Purchasing Department Action
Request Commissioners' Court consideration and any action regarding approval of amendment No. 4 to the contract with Jacobs Engineering Group, Inc. (formerly CH2M Hill Engineers. Inc.), AGR 2015-107, Preparation of Final Plans, Specifications, and Estimates (PS&E) for the Collin County Outer Loop, segment 3A, Dallas North Tollway to East of SH 289, for construction phase services, including direct expenses, to provide part-time project construction inspection for the amount of $775,800.38 and further authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
 Budgeted funds available in the amount of $775,800.38 for Amendment No. 4 to the contract with Jacobs Engineering Group, Inc., AGR 2015-107, Preparation of Final Plans, Specifications, and Estimate for the Collin County Outer Loop, segment 3A, Dallas North Tollway to East of SH 289, for construction phase services. 2007 Bond Fund (4211).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 4 to Preparation of final plans, specifications and estimates for the Collin County Outer Loop, Segment 3Aa (Dallas North Tollway to East of SH289) with Jacobs Engineering Group, Inc. for construction phase services, including direct expenses, to provide part-time project construction inspection and further authorize the Purchasing Agent to finalize and execute same, Special Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $775,800.38
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI07095 4211-750300013-809280
Fund Transfers
Remarks:
Attachments
Court Order
agenda memo
Contract Amendment No. 4
Scope
Fee
2252 Certification