Print Back to Calendar Return
AI- 47056
Commissioners Court
Meeting Date: 09/09/2019  
Authorization to begin negotiations with BGE, Inc for scope/fee for Outer Loop, northerly, west bound Service Road from US75 to FM2478
Submitted For: Clarence Daugherty Submitted By: Teresa Nelson
Department: Engineering  
Request Type: CONSENT Agenda Area: Miscellaneous

Information
Department Action
The Engineering Department submitted a list of projects to be included in the 2019 Bond Sale to Commissioners Court in December 2018 (Court Order # 2018-1089-12-17).  One of the projects on this approved list was the development of Plans, Specifications and Estimates (PS&E) for design of a 9 mile section of service road for the Collin County Outer Loop between U.S. Highway 75 and F.M. Highway 2478 (Custer Road). A budget estimate of $2,915,295 was included for this design work.
 
BGE, Inc. has prepared schematic design plans for this 9 mile section of the Outer Loop.  Their work included preparation of right-of-way parcels, development of typical sections and profiles for both main lanes and service roads.  The design work also included existing and future major cross streets, intersection configurations, ramping, bridge layouts and the location of drainage structures.
 
With this work, BGE demonstrated the ability to provide all services needed for a project of this nature.  Their development of schematic plans for this section of the project provides them with design data, knowledge and very recent familiarity with this specific section of the CCOL.  As such, the Engineering Department has determined that BGE is the best qualified firm to provide design services for the service road connection between U.S. Highway 75 and F.M. Highway No. 2478.
 
Authorization is requested to enter into scope/fee negotiations with BGE, Inc. for design services for the above referenced section of service road and we will be available to answer any questions you might have regarding this matter.
 
Purchasing Department Action
Request Commissioners' Court consideration and any action regarding approval to begin negotiations with Brown & Gay Engineers, Inc., for a scope and fee for the Plans, Specifications and Estimates (PS&E) for the Collin County Outer Loop, Segment 3, from FM 2478 to US Highway 75. Brown & Gay Engineers, Inc. was previously selected by CCTRA Resolution No. 2016-3022-07-19 to provide preliminary engineering, alignment refinement, ROW mapping, and a detailed design schematic for the same section. MD
 
HR and/or IT Action
Budget Department Action
 Budgeted funds available for Plans, Specifications and Estimates for the design of a 9 mile section of service road for the Collin County Outer Loop between US 75 and FM2478.
Auditor's Office Action
Bond funds available.
Commissioners Court

Negotiations with Brown & Gay Engineers, Inc., for a scope and fee for Plans, Specifications and Estimates (PS&E) for the Collin County Outer Loop, Segment 3, from FM 2478 to US Highway 75, Engineering.


Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: negotiations
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL002 4215-750300013-809250
Fund Transfers
Remarks:
Attachments
Court Order
agenda memo
location map

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved