FYI - Change Order No. 3 - 900 E. Park Tax Office Relocation - JM Construction Solutions
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for Change Order No. 3 to Construction, Relocation of Collin County Tax Office, 900 E. Park Blvd., Plano, IFB No. 2019-174 to JM Construction Solutions.
PCO 8- Owner required floor prep in areas where old exam walls were removed. Normal floor prep was included in the contract however when exam room walls were removed we found gaps that needed leveling. $1,870.00
PCO 10 - Owner required change of electronic door hardware. The hardware specified would not attach to the frame because the existing frame was recessed in an existing wall so as not to leave enough room to attach the new hardware. $1, 142.90
In addition 5 days should be added to the contract to perform the work.
Total for this Change Order - $3,012.90 or 0.4% of contract
Total Change Orders for the Project- $14,894.99 or 1.8% of contract
This Change Order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 3 to JM Management LLC, dba JM Construction Solutions, Construction, Relocation of Collin County Tax Office, 900 E. Park, Plano, IFB 2019-174 per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
 Budgeted funds available in the amount of $3,012.90 for Change Order No.3 to IFB 2019-174 with JM Management LLC, dba JM Construction Solutions. New contract total is $870,826.99. 2018 Tax Note Fund (4406).
Auditor's Office Action
Tax Note funds available.
Commissioners Court
Change Order No. 3 to Construction, Relocation of Collin County Tax Office (IFB No. 2019-174) with JM Management, LLC dba JM Construction Solutions to provide various changes to the contract, Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $3,012.90
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI18PLCH-4406-400108033-809101
Fund Transfers
Remarks: