Print Back to Calendar Return
AI- 47742
Commissioners Court
Meeting Date: 12/16/2019  
Request Approval to accept the roads within the Bloomridge phase 1 development (City of McKinney ETJ Subdivision) for county maintenance
Submitted For: Clarence Daugherty Submitted By: Mike Sullivan
Department: Engineering  
Request Type: CONSENT Agenda Area: Miscellaneous

Information
Department Action
  
The plat for the above mentioned subdivision was approved by The City of McKinney and filed on June 9 2017. The infrastructure was completed according to the City of McKinney specifications, which are greater than Collin County specifications. The development was inspected by The City of McKinney and the Collin County Engineering and Public Works staff.
The effective beginning date of the maintenance bond was June 8, 2017 and ended on June 8, 2019. The maintenance period is complete and the owner has completed the required repairs as requested by the Collin County Engineering and Public Works’ staff. If approved, Public Works will place this road on their maintenance lists. The Final Plat is attached.
The Collin County Engineering and Public Works’ staff recommend approval to accept the roads within the Bloomridge phase 1 development (City of McKinney ETJ Subdivision) for county maintenance.
 
Purchasing Department Action
 No action by Purchasing.
HR and/or IT Action
Budget Department Action
No action by Budget. Road maintenance is budgeted in the Road & Bridge Fund (1010).
Auditor's Office Action
No action by Auditor.
Commissioners Court
Accept the roads within the Bloomridge Phase 1 development (City of McKinney ETJ Subdivision) for county maintenance, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Remarks:
Attachments
Court Order
memo
location map
filed plat

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved