FYI to Commissioners' Court for Change Order No. 2 to IS Construction Group, Bid No. 2018-068, Modifications to Sheriff's Office Lobby. CO 2 - County requested credit to change the millwork drawers from plywood to MDF boxes and relocation of outlet due to conflict with existing pipe. Outlet had to be patched and recut in the ballistic material. (Credit $748.00). This change order was previously approved by the County Administrator per Court Order No. 2007-180-02.27.
Total for this Change Order ($748.00)
Total Change Orders for the Project - $4,739.00 or 1.95% of contract.
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 2 to I.S. Construction Group, LLC for IFB 2018-068, Construction, Modifications to Sheriff's Office Lobby for County requested changes to the project per the attached documents. jdg
HR and/or IT Action
Budget Department Action
Change order for a credit of $748. 0499 - Permanent Improvement Fund
Auditor's Office Action
No action by Auditor.
Commissioners Court
Change Order No. 2 to Construction, Modifications to Sheriff's Office Lobby (Contract No. 2018-068) with I.S. Construction Group, LLC to request credit to change in the millwork drawers and the relocation of an outlet, Construction and Projects.