FYI to Commissioners’ Court for Change Order No. 3 to JJ Red Commercial Roofing for the Justice Center Roof Recovery to extend the project completion date by twenty-one calendar days due to weather and no weekend work allowed per change order request by JJ Red Commercial Roofing, LLC dated August 13, 2019. New project completion date: September 11, 2019.
Total for this Change Order – $0.00 or 0% of contract.
Total Change Orders for the Project – ($97,892.72) or (4.6%) of contract.
|