Change Order No. 1: Collin County Central Plant Breaker Relocation, KE Industrial, LLC
Submitted For:
Bill Burke
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners' Court for Change Order No. 1 to KE Industrial, LLC for Collin County Central Plant Breaker Relocation. CO 1 - Engineer requested add to change the location of the new sub-panel based on existing conditions. $5,089.85 or 23.4% of contract. Total for this Change Order - $5,089.85 or 23.4% pf contract. Total Change Order for the Project - $5,089.85 or 23.4% of contract. This change order was approved by County Administrator per Court Order 2007-180-02-27.
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 1 to KE Industrial, LLC for IFB 2019-163, Construction, Collin County Central Plant Breaker Relocation per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $5,089.85 for Change Order No. 1 for IFB 2019-163, Construction, Collin County Central Plant Breaker Relocation.Permanent Improvement Fund (0499).
Auditor's Office Action
Budgeted funds available in the Permanent Improvement Fund.
Commissioners Court
Change Order No. 1 to Construction, Collin County Central Plant Breaker Relocation (IFB No. 2019-163) with KE Industrial, LLC to make various changes to the Invitation for Bid, Construction & Projects.