Change Order No.3 Mario Sinacola & Sons
Submitted For: Clarence Daugherty Submitted By: Dawn Redwine
Department: Engineering  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
The Engineering Department requests approval of Change Order No. 3 to the construction contract with MSSEI for the Outer Loop Project. Change Order No. 3 will allow for proper pavement transitions from the Outer Loop to the existing Coit Rd.
 
Change Order No. 3 results in a net contract increase of $18,812.51 revising the total construction contract amount to $13,321,440.07.
 
Recommended Action:  It is requested that the Commissioners Court approve Change Order No. 3, increasing the Outer Loop contract by $18,812.51, for a total of $13,321,440.07.
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Change Order No. 3 to the contract with Mario Sinacola & Sons Excavating, Inc., IFB 2020-258, Construction, Road, Collin County Outer Loop from East of SH 289 to FM 2478, to allow for proper pavement transitions from the Outer Loop to the existing Coit Rd. for the amount of $18,812.51 and a new total contract amount of $13,321,440.07. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $18,812.51 for Change Order No. 3 to IFB 2020-258, Construction, Road, Collin County Outer Loop from East of SH 289 to FM 2478 with Mario Sinacola & Sons Excavating, Inc.  New contract total is $13,321,440.07. 2018 Bond Fund (4021).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 3 for Construction, Road: Collin County Outer Loop from East of SH 289 to FM 2478 (IFB No. 2020-258) with Mario Sinacola & Sons Excavating, Inc. to add proper transitions from the new Outer Loop project to the existing Coit Road, and further authorize the Purchasing Agent to finalize and execute same, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 18,812.51
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL002-4021-750300013-809280
Fund Transfers
Attachments
Court Order No. 2022-706-08-01
Memo
Change Order No. 3