US 380 Funding Strategy with the Regional Transportation Council
Submitted For: Clarence Daugherty Submitted By: Dawn Redwine
Department: Engineering  
Request Type: CONSENT Agenda Area: Agreement

Information
Department Action
The Regional Transportation Council (RTC) on November 12, 2020, at the request of Collin County, programmed $30,000,000 in federal funds for the Panther Creek Project and $30,000,000 in regional toll revenue funds for the McKinney National Airport Runway Extension Project. The Commissioners Court approved this programming and the allocation of $60,000,000 to the US 380 Project.
 
Attached is an Interlocal Agreement (ILA) between Collin County, the Regional Transportation Council and the North Central Texas Council of Governments (NCTCOG) Executive Board concerning this US 380 Funding Strategy. The funds are available in RI18013-4027-750300013-809683.
 
Recommended Action: It is recommended that the Commissioners Court approve the attached ILA, authorize the County Judge to execute the ILA and authorize payment of $60,000,000 to the NCTCOG/RTC.
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of an Interlocal Agreement 2024-189 between Collin County and the North Central Texas Council of Governments (NCTCOG) concerning Panther Creek Project and McKinney National Airport Runway Extension Project in total payment of $60,000,000. Further, authorize the County Judge to execute same. ED
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $60,000,000 for Interlocal Agreement 2024-189 between Collin County and the North Central Texas Council of Governments for the Panther Creek Project and McKinney National Airport Runway Extension Project. 2018 Bond Fund (4027).
Auditor's Office Action
Bond funds available.
Commissioners Court
Interlocal Agreement with North Central Texas Council of Governments (Agreement No. 2024-189) for the US 380 Funding Strategy concerning the Panther Creek Project and McKinney National Airport Runway Extension Project, and payment in the amount of $60,000,000 for same, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 60,000,000
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18013-4027-750300013-809683