AI- 56019
Commissioners Court
Meeting Date: 06/03/2024  
Change Order No.1 to with RPMx Construction, LLC Collin County Outer Loop Segment 3C
Submitted For: Clarence Daugherty Submitted By: Dawn Redwine
Department: Engineering  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
TThe Engineering Department requests approval of Change Order No. 1 to the construction contract with RPMx for the CCOL3C Project. Change Order No. 1 will allow for drill shaft cores to be performed per TxDOT Specifications, an electric gate and cattle guard, additional bridge deck steel and steel casing for a drill shaft at the East Fork Trinity River bridge. The change order will remove the monitoring well termination item since this work was done by others.
 
Change Order No. 1 results in a net contract increase of $229,071.64 revising the total construction contract amount to $62,312,797.94. 
 
$88,335.78 is available in RI18OL002-4021-750300013-809280
$140,735.86 is available in RI18OL002-4030-750300013-809280
 
Recommended Action:  It is requested that the Commissioners Court
-approve Change Order No. 1, increasing the CCOL3C contract by $229,071.64, for a total construction contract amount of $62,312,797.94.
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of change order No. 1 to the contract with RPMx Construction, LLC, IFB 2023-303, Construction, Collin County Outer Loop Segment 3C from FM 2478 to US 75, to add drill shaft cores, an electric gate and cattle guard, additional slab reinforcement, a permanent 36" drill shaft casing, and to delete one gate and the capping and terminating of a monitoring well for the total amount of $229,071.64 and a new total contract amount of $62,312,797.94. Further, authorize the Purchasing Agent to execute same. MD 
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $229,071.64 for Change Order No. 1 to IFB 2023-303, Construction, Collin County Outer Loop Segment 3C from FM 2478 to US 75 with RPMx Construction, LLC.  New contract total is $62,312,797.94. 2018 Bond Fund (4021 & 4030).
Auditor's Office Action
2018 Bond funds available (4021 & 4030).
Commissioners Court
No. 1 to Construction, Collin County Outer Loop Segment 3C from FM 2478 to US 75 (IFB No. 2023-303) with RPMx Construction, LLC to provide various changes to the contract and further authorize the Purchasing Agent to finalize and execute same, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 229,071.64
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL002-4021/4030-750300013-80928
Fund Transfers
Remarks:
Attachments
Court Order 2024-506-06-03
Memo
Change Order No. 1
Change Order #1-BGE
Form 1295
2252 Certification

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved