Print Back to Calendar Return
AI- 49603
Commissioners Court
Meeting Date: 01/04/2021  
Contract Amendment No. 9 Frontier Pkwy Engineering Services Agreement
Submitted For: Clarence Daugherty Submitted By: Clarence Daugherty
Department: Engineering  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
Two amendments to Birkhoff, Hendricks and Carter’s (BHC) contract are needed.
 
The scope of the current agreement with BHC assumes that the process for selecting a contractor would be the typical low-bid process. However, it was determined that the Competitive Sealed Proposal process would be the best was to select a contractor for this particular project. That process required additional work by BHC which is explained in the attached amendment proposal. This is styled Amendment No. 9, and is an increase of $46,286. The Interlocal agreement we have with the Town of Prosper and the City of Celina requires this amount to be shared by the County and the two municipalities (one-third each).
 
Also the Town of Prosper has proposed that a “Project Visualization” effort for this project. This effort provides a video that shows the “before and after” of the improvements to the project. It is extremely useful in communicating to the public the nature of the improvements to expect when the project is completed. It, of course, will also help the Councils and Commissioners Court to see the improvements as well. The cost of this is consists of the video creation by RDV Systems, Inc., as a sub-consultant to BHC, as well as additional tasks performed by BHC to provide RDV the materials it needs to create the video. This is styled as Amendment No. 10, and is an increase of $42,850. The Interlocal agreement we have with the Town of Prosper and the City of Celina requires this amount to be shared by the County and the two municipalities (one-third each).
 
These amendments require a budget adjustment in order to move funds within the project to the appropriate object code. The requested adjustment is shown below.
 
Action Requested: It is requested that Commissioners Court approve Amendment No. 9 and Amendment No. 10 the Frontier Parkway Engineering Services Agreement with Birkhoff, Hendricks and Carter and authorize the following budget adjustment:
 
From: RI07014  4213-750300013-809280, $89,136
 
To: RI07014  4213-750300013-809250, $89,136
 
Purchasing Department Action
Request Commissioners' Court consideration and any action regarding approval of contract amendment No. 9 to the contract with Birkhoff, Hendricks & Carter, LLP, AGR 2016-229, Frontier Parkway Improvements, for additional scope as per the attached proposed engineering amendment No. 9 and No. 10 for a total increase of $89,136.00 and new total contract value of $2,588,854.00. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Requesting Contract Amendment No. 9 to AGR 2016-229, Frontier Parkway Improvements with Birkhoff, Hendricks & Carter, LLP totaling $89,136 to add Engineer's Amendments 9 & 10. Budget Adjustment included in the amount of $89,136 to move the funding to the appropriate expenditure line.  New Contract Total is $2,588,854. 2007 Bond Fund (4213).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 9 to Frontier Parkway Improvements (Agreement No. 2016-229) with Birkhoff, Hendricks & Carter L.L.P. for additional scope and further authorize the Purchasing Agent to finalize and execute same, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 89,136
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI07014-4213-750300013-809250
Fund Transfers
Remarks:
Attachments
Court Order 2021-016-01-04
Department Memo
Amendment
Contract Amendment No. 9
ESA Amendment 9
ESA Amendment 10
Form 1295
2252 Certification
Budget Adjustment

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved