Back to Calendar
Return
|
AI- 51391 |
|
Commissioners Court |
|
|
Information |
Department Action |
The Engineering Department requests the approval of Amendment No. 13 to the Engineering Services Agreement (ESA) with Birkhoff Hendricks and Carter (BHC). This amendment will account for additional Construction Administration, ROW Maps, Plats and Field Notes, Geotechnical Investigations and Utility Coordination in the amount of $70,728 and will be split between Collin County, City of Celina and Town of Prosper ($23,576.00 each). This additional work is needed because the project was delayed by several months due to utility conflicts. During this time, BHC has been fully involved with the project.
The City of Celina and Town of Prosper would also like to add design services for Developer Initiated Driveways and Median Openings in the amount of $38,450.00. This cost will be split by the City of Celina and Town of Prosper.
The net change is adding $109,178.00 to the contract, to cover the additional design and construction administration efforts, revising the total contract amount to $2,762,232.00.
Action Requested: It is recommended that Commissioner’s Court
- approve Collin County’s Amendment No. 13 for the Frontier Parkway Engineering Services Agreement with Birkhoff, Hendricks and Carter.
- authorize the Auditor to transfer funds from Celina and Prosper (totaling $85,602.00) to RI07014-4202-750300013-809250
-County’s portion ($23,576.00) is available in RI07014-4202-750300013-809250
|
Purchasing Department Action |
Request Commissioners Court consideration and any action regarding approval of Amendment No. 13 to the Engineering Services Agreement with Birkhoff, Hendricks & Carter, LLP, Frontier Parkway Improvements (AGR 2016-229), for additional Construction Administration, ROW Maps, Plats and Field Notes, Geotechnical Investigations and Utility Coordination in the amount of $70,728 split between Collin County, City of Celina and Town of Prosper ($23,576.00 each) and City of Celina and Town of Prosper design services for Developer Initiated Driveways and Median Openings in the amount of $38,450.00, split evenly by the City of Celina and Town of Prosper for an amendment total of $109,178.00 and a new total contract amount of $2,762,232.00. Further, authorize the Purchasing Agent to execute same. MD |
HR and/or IT Action |
|
Budget Department Action |
Amendment No. 13 to AGR 2016-229, Frontier Parkway Improvements with Birkhoff Hendricks and Carter, LLP for additional construction administration, right of way maps, plats and field notes, geotechnical investigations and utility coordination totaling $70,728 to be split equally between the County, Celina and Prosper. Design services for Developer Initiated Driveways and Median Openings are also being added totaling $38,450 and will be split between Celina and Prosper. Celina and Prosper will be sending money for their portions of the amendment and once deposited a Budget Amendment to budget the funds will be needed totaling $85,602. Collin County's participation in the amendment is budgeted and will total $23,576. New contract total is $2,762,232. 2007 Bond Fund (4202). |
Auditor's Office Action |
Funding to be received from City of Celina and the Town of Prosper. Budget Amendment to allocate funding to expense accounts will be entered upon receipt of funding.
|
Commissioners Court |
No. 13 to Frontier Parkway Improvement (Agreement No. 2016-229) with Birkhoff Hendricks & Carter to provide various changes to the contract, further authorize the Purchasing Agent to finalize and execute same and budget amendment in the amount of $86,602 when funds are received, Engineering. |
|
Budget Information |
Information about available funds |
Budgeted: |
Funds Available: |
Adjustment: |
Amount Available: |
109,178 |
Unbudgeted: |
Funds NOT Available: |
Amendment: |
|
Fund Transfers |
Remarks: |
|
|
|