Change Order No. 4 to Sedalco Inc. for CCADF Medical Mental Health Expansion
Submitted For:
Sandeep Kathuria
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
CONSENT
Agenda Area:
Change Order
Information
Department Action
Request Commissioners Court approval of Change Order No. 4 to Sedalco, Inc for Contract NO. 2023-398, Construction: CCADF Medical Mental Health Expansion.
PCO #004 – Credit associated with the use of PVC pipe in lieu of cast iron for all sanitary and storm sewer pipe throughout the project. ($182,870.00)
PCO #007 – Engineer required revisions issued by ASI #001 to shorten six piers by 1’-2” and 1’-2” deeper grade beams $8,236.02. This change order will add 2 days to the schedule.
PCO #008 – City of McKinney required add for gate valve on the main water line at Community Avenue. $5,800.39
PCO #009 – Credit associated with the use of an alternate approved product for mechanical insulation lapping per RFI #029. ($74,360.00)
This change order will add 2 days to the schedule.
Total amount of this change order is a credit of ($243,193.59) or (0.023%) of contract.
Total Change Orders for this Project - $356,513.18 or 0.034% of contract.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Change Order No. 4 to Sedalco, Inc. for CSP 2023-398 CCADF Medical Mental Health Expansion, per the attached documents. Further, authorize the Purchasing Agent to execute the change order. (ha)
HR and/or IT Action
Budget Department Action
Request for approval of Change Order No. 4 to 2023-398, Construction: CCADF Medical Mental Health Expansion with Sedalco, Inc. Change order credit ($243,193.59). ARPA Fund (2132).
Auditor's Office Action
No action required by Auditor.
Commissioners Court
No. 4 to CCADF Medical Mental Health Expansion (CSP No. 2023-398) with Sedalco, Inc. to make various changes to the contract, and further authorize the Purchasing Agent to finalize and execute same, Construction & Projects.
Budget Information
Information about available funds
Budgeted:
Funds Available:
Adjustment:
Amount Available:
Unbudgeted:
Funds NOT Available:
Amendment:
Account Code(s) for Available Funds
1:
GTARPADC-2132-040010059-809110
Fund Transfers
Remarks:
CREDIT
Attachments
Court Order 2024-637-07-15
Memo
Change Order No. 4
PCO 4
PCO 7
PCO 8
PCO 9
2252 Certification
1295 Form - redacted
AgendaQuick©2005 - 2025 Destiny Software Inc., All Rights Reserved