Contract Amendment No 2 with Jacobs Eng., for CCOL East Bound Frontage Rd Design; Contract No 2019-269
Submitted For: Jeff Durham Submitted By: Teresa Nelson
Department: Special Projects  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
The Engineering Department requests that the contract with Jacobs Engineering for services relating to design of the CCOL east bound (southern) service road be increased by $9,897.25.  This increase is for surveying services necessary for the preparation of drainage easements and right-of-way staking for fence relocations.
 
Since neither of these tasks were part of Jacobs original scope, inclusion of the attached Supplemental Scope of Services is also requested.
 
Commissioners Courts approval of this contract amendment and Supplemental Scope of Services is requested and I will be available to answer any questions you might have regarding this matter.
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of contract amendment No. 2 to the contract with Jacobs Engineering Group, Inc., AGR 2019-269, Preparation of Final Plans, Specifications and Estimates (PS & E) for the Collin County Outer Loop, Segment 3B East of Preston Rd (SH 289) to Custer Rd (FM 2478), to add the preparation of easement documents and right-of-way staking for fence relocations for the amount of $9,897.25. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
 Budgeted funds available in the amount of $9,897.25 for Amendment No. 2 to the contract with Jacobs Engineering Group, Inc., AGR 2019-269, Preparation of Final Plans, Specifications and Estimates for the Collin County Outer Loop, Segment 3B East of Preston Rd (SH 289) to Custer Rd. (FM 2478) to add the preparation of drainage easements and right-of-way staking for fence relocations. 2018 Bond Election (Fund 4215).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 2 to Preparation of final plans, specifications and estimates (PS & E) for the Collin County Outer Loop, Segment 3B East of Preston Rd (SH 289) to Custer Rd (FM 2478) (Contract No. 2019-269) with Jacobs Engineering Group, Inc. to add the preparation of easement documents and right-of-way staking for fence relocations, and further authorize the Purchasing Agent to finalize and execute same, Special Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $9,897.25
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL002-4215-750300013-809250
Fund Transfers
Remarks:
Attachments
Court Order
agenda memo
Contract Amendment 2
additional scope
Supplemental Fee Schedule
2252 Certification

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved