Change Order No. 3 with Mario Sinacola & Sons Excavating, Inc.
Submitted For: Clarence Daugherty Submitted By: Dawn Redwine
Department: Engineering  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
The Engineering Department requests that the contract with MSSEI be adjusted to allow for additional improvements to the Outer Loop project.
 
One of the improvements is the work required to revise the median nose to a laydown nose at the Dallas North Tollway (DNT) and Outer Loop intersection. Due to heavy truck traffic, we were concerned with large vehicles breaking median nose curbs while turning. We believe a laydown nose will be beneficial to the project and less maintenance.
 
In addition, we felt that additional signage added to four stop signs warning drivers that cross traffic does not stop would aid in increased safety. Jacob’s traffic engineer agreed and recommended adding Texas Manual on Uniform Traffic Control Device (TMUTCD) approved signage.
 
Change Order No. 3 results in a net contract increase of $18,633.15. The new total of the contract will be $18,607,289.27.
 
Attached is the Change Order Documentation.
 
Action:
It is requested that the Commissioners Court approve Change Order No. 3 for Outer Loop Access Road (Limits from DNT to SH 289) in the amount of $18,633.15, and authorize execution by the County Judge.
 
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of change order No. 3 to the contract with Mario Sinacola & Sons Excavating, Inc., IFB 2019-109, Construction, Road, Outer Loop Access Road, Dallas Parkway to East of SH 289, for revision to the median nose at the Dallas Parkway and Outer Loop intersection and additional signage for the amount of $18,633.15 for a new total contract of $18,607,289.27. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Budgeted funds available for Change Order No. 3 in the amount of $18,633.15 to IFB 2019-109, Construction, Road, Outer Loop Access Road, Dallas Parkway to East of SH 289 with Mario Sinacola & Sons Excavating, Inc.  New contract total is $18,607,289.27. 2007 Bond Fund (4210).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 3 to Construction, Road: Outer Loop Access Road, Dallas Pkwy. to East of SH 289 (IFB No. 2019-109) with Mario Sinacola & Sons Excavating, Inc. to make various changes to the contract, and further authorize the Purchasing Agent to execute and finalize same, Engineering. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 18,633.15
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI07095-4210-750300013-809280
Fund Transfers
Remarks:
Attachments
Court Order 2021-1143-11-08
Memo
Change Order No. 3
Change Order Backup