FYI Change Order No. 1 to Criterion Contractors, Inc
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners Court for Change Order No. 1 to Criterion Contractors, Inc for Construction, Modifications to Precinct 3 Constable and Justice of the Peace, 920 E. Park Blvd. (IFB No. 2021-129). 
PCO 1 -Architect requested add to install toilet accessories to the Jury restroom not shown on the plans. $2,255.00 
PCO 2 - Architect requested add to install a pendant Light fixture in the Courtroom not shown on the plans. $3,437.50 
PCO 3 -Owner requested add to install electrical power for a second water heater instead of switching out with the existing water heater to split the service between the two floors. $1,147.30 
PCO 4 - Owner requested add to install slant panels under the restrooms for aesthetic purposes. $1,650.00 
PCO 5 -Architect requested add to install end panels in the restroom millwork no shown on the plans. $742.50 
Total for this Change Order - $9,232.30 or 1.21 % of contract 
Total Change Orders for the Project - $9,232.30 or 1.21 % of contract 
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 1 to Criterion Contractors, Inc. for Construction, Modifications to Precinct 3 Constable & Justice of the Peace, 920 E. Park Blvd., IFB 2021-129 per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg 
 
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $9,232.30 for Change Order No. 1 to IFB 2021-129, Construction, Modifications to Precinct 3 Constable & Justice of the Peace, 920 E. Park Blvd. with Criterion Contractors, Inc.  New contract total is $774,299.30. 2018 Tax Notes (4406).
Auditor's Office Action
Tax Note funds available.
Commissioners Court
Change Order No. 1 to Construction, Modifications to Precinct 3 Constable & Justice of the Peace, 920 E. Park Blvd. (IFB No. 2021-129) with Criterion Contractors, Inc. to make various changes to the contract, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $9,232.30
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI18PLCH-0499-400108019-809101
Fund Transfers
Remarks:
Attachments
Memo
PCOs
Change Order 1

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved