Print Back to Calendar Return
AI- 51548
Commissioners Court
Meeting Date: 02/07/2022  
Amendment to Contract with BGE, Inc., for additional design efforts on the Outer Loop Project (FM 2478 to SH 75)
Submitted For: Clarence Daugherty Submitted By: Dawn Redwine
Department: Engineering  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
The Engineering Department requests the approval of Amendment No. 2 to the Engineering Services Agreement (ESA) with BGE, Inc. As the Outer Loop (FM 2478 to SH 75) Project has been brought further into design, BGE has identified two locations of the service road that will have steep slopes requiring retaining walls or additional easements for grading, thus increasing the construction and/or ROW costs of the project. It was determined and recommended that in the areas where these grade issues were occurring, the alignment of the service road can slightly shift away from the ROW in order to eliminate the need for retaining walls or additional property easements. This change was a less expensive option.
 
In addition to the alignment shift, BGE will be providing exhibits to aid in Access Control. Over the course of the design of this project, several property owners and potential property investors have been looking to develop their parcels and have been inquiring on where driveways can be placed to have access to the Outer Loop. These Access Control Exhibits will assist the County in determining/permitting driveway access along the Outer Loop while maintaining TxDOT Access Management Standards in the interim and ultimate conditions for Outer Loop. 
 
The net change is adding $146,927.00 to the contract, to cover the additional design efforts. Currently, there is $0.62 available in in the consulting account.  Therefore, the remainder needed for this amendment, $146,926.38, needs to be moved from within the project to the consulting account with a budget adjustment.
 
Action Requested: It is requested that Commissioners Court approve the attached Amendment No. 2 and a budget adjustment to transfer $146,926.38
 
From: RI18OL002-4215-750300013-809682
 
To:     RI18OL002-4215-750300013-809250
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of contract amendment No. 2 to the contract with BGE, Inc., AGR. 2020-049, Collin County Outer Loop, Segment 3A Access Rd. PS&E from FM 2478 to US 75, for additional services to shift alignment at two locations of the service road and provide exhibits for access control for an additional fee of $146,927.00 for a new total contract amount of $2,399,973.22. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Funds available in the amount of $146,927 for Contract Amendment No. 2 to AGR 2020-049, Collin County Outer Loop, Segment 3A Access Road PS&E from FM 2478 to US 75 with BGE, Inc.  Budget Adjustment included in the amount of $146,926.38 to move the funds to the appropriate expenditure account within the project.  2018 Bond Fund (4215).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 2 to Collin County Outer Loop Segment 3 Access Road PS&E from FM 2478 to US 75 (Contract No. 2020-049) with BGE, Inc. to add services to shift the alignment at two locations of the service road and provide exhibits for access control, and further authorize the Purchasing Agent to finalize and execute same; budget adjustment in the amount of $146,927, Engineering. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 146,927
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL002-4215-750300013-809682
Fund Transfers
Remarks:
Attachments
Court Order 2022-094-02-07
Memo
Scope and Fee
Amendment No. 2
Form 1295
2252 Certification
Journal Proof

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved