Print Back to Calendar Return
AI- 53570
Commissioners Court
Meeting Date: 02/13/2023  
Award: Construction, Collin County Adult Detention Facility, Phase 2 Central Utility Plant
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: CONSENT Agenda Area: Award

Information
Department Action
Request Commissioners’ Court consideration and approval to award: IFB 2022-299 Construction: Collin County Adult Detention Facility, Phase 2 Addition, Central Utility Plant to the lowest and best bid meeting specifications.
 
Purchasing Department Action
Request Commissioners Court consideration any action to award IFB 2022-299 Construction: Collin County Adult Detention Facility, Phase 2 Addition, CUP to Sedalco Inc, the best and lowest bid meeting specifications and authorize Purchasing Agent to finalize and execute the Construction Agreement. ha
HR and/or IT Action
Budget Department Action
Funds available in the amount of $25,482,522 for the award of IFB 2022-299 Construction, Collin County Adult Detention Facility, Phase 2 Addition, Central Utility Plant.  Budget Adjustment totaling $6,033,103.82 is included to move funding to the appropriate accounts for the award and to include a 5% contingency.  ARPA Fund (2132).
Auditor's Office Action
Budget amendment completed in the amount of $6,033,103.82 as per attached to add additional funds to the project budget. 
Commissioners Court
Construction: Collin County Adult Detention Facility, Phase 2 Addition, CUP (IFB No. 2022-299) to Sedalco, Inc. and further authorize the Purchasing Agent to finalize and execute the Construction Agreement for same; budget adjustment in the amount of $6,033,103.82, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $25,482,522
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: GTARPACPB-2132-040010059-809110
Fund Transfers
Remarks:
FY 2023 Budget Adjustment Totaling $6,033,103.82.
Attachments
Court Order 2023-114-02-13
Memo
Contract Data Sheet
Bid Tabulation
Award Letter_r
Agreement
2252 Certification
1295 Form - redacted
Journal Proof

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved