Meeting Date: 04/05/2021  
Change Order No. 2, Sheriff's Office Computer Room Air Conditioning, Denali CS
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for Change Order No. 2, Collin County Sheriff's Office Computer Room Air Conditioning Replacement, IFB 2020-346 for PCO 2 - Engineer requested change to remove and replace 40 If. of refrigerant line to one of three Liebert units. Lines were to remain, however manufacturer stated one of the lines was too small. $3,817.29 
The contractor request to add seven (7) days to the contract because of time delays due to RFI and PCO response time. New completion date will be April 6, 2021.
Total for this Change Order - $3,817.29 or 3.58% of contract 
Total Change Orders for the Project- $7,369.79 or 6.92% of contract 

 
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 2 to Denali Construction Services, LP for Construction, Collin County Sheriff's Office Computer Room Air Conditioning Replacement, IFB 2020-346, per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $3,817.29 for Change Order No. 2 to IFB 2020-346, Construction, Collin County Sheriff's Office Computer Room Air Conditioning Replacement with Denali Construction Services, LP to replace refrigerant line and add 7 days to the contract. New contract total is $113,903.79. General Fund (0001).
Auditor's Office Action
Funds available in the General Fund.
Commissioners Court
Change Order No. 2 to Construction, Collin County Sheriff's Office Computer Room Air Conditioning Replacement (IFB No. 2020-346) with Denali Construction Services, LP to make various changes to the contract, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $3,817.29
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: BDL4004-0001-400300001-809120
Fund Transfers
Remarks:
 