03/21/2022
Change Order No. 2 to IFB 2021-084
Submitted For:
Jon Kleinheksel
Submitted By:
Tammi Koch
Department:
Public Works
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners Court for Change Order No. 2 to HQS Construction, LLC adding 38 days to the contract due to weather and holidays. This is a new completion date of 3/4/22.
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 2 to IFB 2021-084 CR317 (Orr Rd) from Stacy Rd South to NTMWD Driveway with HQS Construction, LLC to add additional construction days to the contract per the attached documentation. gz
HR and/or IT Action
Budget Department Action
Budgeted funds available for Change Order No. 2 to IFB 2021-084 Construction, Road: County Road 317 (Orr Rd) from Stacy Rd South to NTMWD Drive with HQS Construction, LLC. Change order to extend the project completion date due to weather and holidays. (1010)-Road and Bridge Fund.
Auditor's Office Action
Funds available in the Road and Bridge Fund.
Commissioners Court
Change Order No. 2 to CR 317 (Orr Road) from Stacy Rd South to NTMWD Driveway (IFB 2021-084) with HQS Construction, LLC to add additional construction days to the contract, Public Works.
Budget Information
Information about available funds
Budgeted:
Funds Available:
Adjustment:
Amount Available:
$9,524,000
Unbudgeted:
Funds NOT Available:
Amendment:
Account Code(s) for Available Funds
1:
1010-75001-0001-68-30-0000-637529-
2:
1010-75001-0001-68-30-0000-637532-
Fund Transfers
Remarks:
Attachments
memo
Contractor request
Change Order 2