Meeting Date: 01/09/2023  
FYI Change Order No. 9 to Ratcliff Construction for Construction, Collin County Adult Detention Facility, Phase 1 Addition
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners Court for contract change order No. 9 to Ratcliff Constructors for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
PCO 27 – Owner requested change to remove metal curbs from two small areas.  Consensus between the Owner and Architect determined concrete was the better choice here.  $0
PCO 32 – Owner requested add for additional bollards to protect the entrance to the sally port.  The sally port already had bollards but the angle of entry led us to add more. $1,548.64
PCO 33 – Engineer requested slab edge adjustments.  Additional steel added to support the slab during review of shop drawings. $13,369.65
Total for this change order – $14,918.29 or 0.039% of contract
Total changes for this contract – ($157,325.96) or (0.41%) of contract
 
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 9 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg   
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $14,918.29 for Change Order No. 9 to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase I with Ratcliff Constructors. New contract total is $38,102,674.04. 2007 Bond Fund (4020).
Auditor's Office Action
Bond funds available.
Commissioners Court
Change Order No. 9 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to make various changes to the contract, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $14,918.29
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI07JAIL-4020-400308002-809101
Fund Transfers
Remarks:
Attachments
Memo
PCO 27
PCO 32
PCO 33
Change Order 9