Change Order No. 2 To Ratcliff Construction, Collin County Adult Detention Facility, Phase 1 Addition
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
Request Commissioners Court consideration and approval of Change Order No. 2 to Ratcliff Construction for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1.
PCO 1 – Owner requested credit of roof equipment screening removed by City of McKinney variance.  At the time of the bid, we had not received the variance so we decided to leave the screening in the bid as an alternate.  We received the variance after Commissioners Court accepted the bid.  ($330,000.00)
PCO 3 – City required Storm sewer changes after bidding finalized.  The City requested these changes on the second submission of the Engineering plans. (141,688.28); plus add fourteen days to the contract. The completion date was 1/28/2024 and the new completion date is 2/11/2024.
Total for this Change Order – ($188,311.72) or (0.49%) of contract
Total Change Orders for the Project – ($169,347.10) or (0.44%) of contract
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Contract Change Order No. 2 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition per the attached documents. Further authorize the Purchasing Agent to execute the contract change order. jdg
HR and/or IT Action
Budget Department Action
Request for Change Order No. 2 in the amount of ($188,311.72) to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase I with Ratcliff Construction. New contract total is $38,090,652.90. 2007 Facility Bonds (4020).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 2 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to make various changes to the contract, and further authorize the Purchasing Agent to finalize and execute same, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: ($188,311.72)
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI07JAIL-4020-400308002-809101
Fund Transfers
Remarks:
CREDIT
Attachments
Court Order 2022-358-04-18
Memo
PCO 1
PCO 3
Form 1295
2252 Certification
Change Order 2

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved