Print Back to Calendar Return
AI- 53776
Commissioners Court
Meeting Date: 04/03/2023  
Contract with BGE, Inc.,Outer Loop Project (FM 2478 to SH 75)
Submitted For: Clarence Daugherty Submitted By: Dawn Redwine
Department: Engineering  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
The Engineering Department requests the approval of Amendment No. 3 to the Engineering Services Agreement (ESA) with BGE, Inc. Amendment No. 3 will cover the additional work necessary to comply with the mitigation requirements per the Natural Resources Conservation Service (NRCS) due to a SCS lake easement encroachment, subsurface utility exploration (SUE) for a 2” waterline that had no as-built information and right-of-way (ROW) staking for utility relocations.
 
The amendment is adding $165,608.00 to the contract, to cover the additional design efforts. Currently, there is $0.62 available in in the consulting account.  Therefore, this amendment will need a budget adjustment to move funds from within the project to the consulting account.
 
Action Requested: It is requested that Commissioners Court approve the attached Amendment No. 3 and a budget adjustment to transfer $165,608.00
 
From: RI18OL002-4215-750300013-809682
 
To:     RI18OL002-4215-750300013-809250
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Amendment No. 3 to the contract with BGE, Inc., AGR 2020-049, Collin County Outer Loop Segment 3A Access Road PS&E from FM 2478 to US75, for additional work necessary to comply with the mitigation requirements per the Natural Resources Conservation Service (NRCS) due to a SCS lake easement encroachment, subsurface utility exploration (SUE) for a 2” waterline that had no as-built information, and right-of-way (ROW) staking for utility relocations for the amount of $165,608.00, resulting in a revised total contract amount of $2,565,581.22. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Requesting approval of Amendment No. 3 to AGR 2020-049, Collin County Outer Loop Segment 3A Access Road PS&E from FM 2478 to US75 with BGE, Inc. in the amount of $165,608.  Budget Adjustment included in the amount of $165,608 to move the funds to the appropriate expenditure account within the project. New contract total is $2,565,581.22. 2018 Bond Fund (4215).
Auditor's Office Action
Bond funds available.  Budget amendment will be processed upon approval.
Commissioners Court
No. 3 to Collin County Outer Loop Segment 3A Access Road PS&E from FM 2478 to US 75 (Agreement No, 2020-049) with BGE, Inc. to add services for mitigation requirements and further authorize the Purchasing Agent to finalize and execute same, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 165,608
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL002-4215-750300013-809250
Fund Transfers
Remarks:
FY 2023 Budget Adjustment Totaling $165,608.
Attachments
Court Order 2023-265-04-03
Memo
Amendment No. 3.pdf
Fee Estimate Pond
Fee Estimate SUE
Fee Estimate Breakdown
Supplemental Memo
2252 Certification
Form 1295
Journal Proof

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved