Commissioners Court
Meeting Date: 04/10/2023  
No. 12 to Ratcliff Constructors for Construction, Collin County Adult Detention Facility
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
Request Commissioners Court consideration and approval for contract change order No. 12 to Ratcliff Constructors for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1.
PCO 18 – Add to connect to existing storm drain.  Storm drain, found during construction, ran under the existing building.  Part of the cost includes redesign of grade beams to avoid the existing drain. $107,231.30
PCO 40 – City of McKinney required exploratory digging to determine responsibility for water leak.  It was determined that the City was responsible for, the leak, but they will not pay for the exploration. $1,277.16
PCO 42 – City required change of floor drains at tier level floor drains.  Cost is for material only.  $4,272.10
PCO 46 – Owner requested change to add bond beams to open the masonry wall from the exterior.  This will allow better access to buildout the shell space in the future. $3,030.80
Total for this change order – $115,811.36 or 0.30% of contract
Total changes for this contract – ($1,486.19) or 0.001% of contract
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Contract Change Order No. 12 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition per the attached documents. Further, authorize the Purchasing Agent to execute the contract change order. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available for Change Order No. 12 to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 with Ratcliff Constructors, L. P. in the amount of $115,811.36. New contract total is $38,258,513.81. 2007 Bond Fund (4020).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 12 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to provide various changes to the contract, and further authorize the Purchasing Agent to finalize and execute same, Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $115,811.36
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI07JAIL-4020-400308002-809101
Fund Transfers
Remarks:
Attachments
Court Order 2023-286-04-10
Memo
PCO 18
PCO 40
PCO 42
PCO 46
Change Order 12
2252 Certification
Form 1295

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved