Print Back to Calendar Return
AI- 53973
Commissioners Court
Meeting Date: 05/08/2023  
FYI Change Order No. 13 to Ratcliff Constructors for Construction, Collin County Adult Detention Facility, Phase 1 Addition
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners Court for contract change order No. 13 to Ratcliff Constructors for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1. This change order was previously approved by the County Administrator per Court Order NO. 2007-180-02-27. PCO 41 -Add to modify, and expand, existing Recreation yard curbs. It was determined during shop drawing review that extending the curbs would allow better water protection for the first level once the traffic coating is applied. $18,265.73  PCO 44 - Credit for unused formwork for 2" depression in one holding cell. The depression was removed from scope. ($255.97)  PCO 47 -Credit to reimburse Latta Tech for travel expenses to San Antonio to witness factory test of equipment. A corresponding add will be given to the Architects contract to get the funds to the Security Designer. ($862.57)  PCO 48 -Architect requested add to include more waterproofing at expansion joints with the existing building. When brick was removed, it was determined that more waterproofing is needed. $4,774.00. This change order adds 36 days to the schedule pertaining to PR#4/PCO 18, and one day per PCO#048 for a total of 37 days. Previous completion date of 3/4/24. New completion date of 4/10/24.  Total for this change order -$21,921.19 or 0.057% of contract  Total changes for this contract -$20,435.00 or 0.057% of contract 
Purchasing Department Action
FYI notification to Commisioners Court of Contract Change Order No. 13 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. mlm
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $21,921.19 for Change Order No. 13 to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase I with Ratcliff Constructors, L.P. New contract total is $38,280,435. 2007 Bond Fund (4020).
Auditor's Office Action
Bond funds available.
Commissioners Court
Change Order No. 13 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to make various changes to the contract, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $21,921.19
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI07JAIL-4020-400308002-809101
Fund Transfers
Attachments
Memo
PCO 41
PCO 44
PCO 47r
PCO 48
Change Order 13

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved