Print Back to Calendar Return
AI- 54030
Commissioners Court
Meeting Date: 05/22/2023  
No. 14 to Ratcliff Constructors for Construction, Collin County Adult Detention Facility, Phase 1
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
Request Commissioners Court consideration and approval for contract change order No. 14 to Ratcliff Constructors for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1.
PCO 38 – Owner requested add to feed HVAC and Electric to the future female pod.  At bid time, we did not know if we could afford to do this work.  Since funds are available, we would like to get this done now instead of interrupting operations when constructing the addition. This will add 21 days to the schedule.  $217,302.83
PCO 45 – Owner requested add to change a floor drain to a flushing floor drain.  This area will be a calming cell and requires a flushing drain. This will add 3 days to the schedule.  $4,827.31
PCO 49 – Owner requested add to install sleeves and a weather head to run cabling for the Motorola antenna system on construction is completed. This will add 1 day to the schedule. $8,108.01
 PCO 50 – Architect requested add to include through wall flashing at the top of the retaining wall.  This added flashing will keep moisture out of the space between the retaining wall and the corridor extending from the existing building this will add 1 day to the schedule.  $2,018.28
This change order adds a total of 26 days to the schedule. Previous completion date 4/10/24. New completion date 5/6/24.
Total for this change order – $232,256.43 or 0.61% of contract
Total changes for this contract – $252,691.43 or 0.66% of contract
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Contract Change Order No. 14 to Ratcliff Constructors, L.P. for IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition per the attached documents. Further, authorize the Purchasing Agent to execute the contract change order. mlm 
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $232,256.43 for Change Order No. 14 to IFB 2021-239, Construction, Collin County Adult Detention Facility, Phase 1 Addition with Ratcliff Constructors, L.P.  New contract total is $38,512,691.43. 2007 Bond Fund (4020).
Auditor's Office Action
Budgeted Bond funds available.
Commissioners Court
No. 14 to Construction, Collin County Adult Detention Facility, Phase 1 Addition (IFB No. 2021-239) with Ratcliff Constructors, L.P. to provide various changes to the contract and further authorize the Purchasing Agent to finalize and execute same, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $232,256.43
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI07JAIL-4020-400308002-809101
Fund Transfers
Remarks:
Attachments
Court Order 2023-420-05-22
Memo
PCO 38
PCO 45
PCO 49
PCO 50
Change Order 14
2252