AI- 51820
Commissioners Court
Meeting Date: 03/28/2022  
Change Order No. 3 to Construction, New Office Building for Precinct 2, M-PAK Construction
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for Change Order No. 3 to IFB 2020-272, Construction, New Office Building for Precinct 2, M-PAK Construction. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
PCO 5 - TX dot required add to rent safety truck for work in right of way not shown in bid documents. $6,721.55 
PCO 6 - TX dot required add for field changes to rebar and concrete thickness not shown in bid documents. $23,831.85 
PCO 8 - Owner requested credit for change of light fixture scheduled for courtroom. ($962.50) 
PCO 9 - Reimbursement of inspection/permit fee for waterline installation. $2,906.30 PCO 10 - Owner requested credit for roofing cover board not required for 30-year warranty. ($3,811.64) 
PCO 11 - Owner requested add for 30 amp circuit and two additional roof penetrations in data closet for UPS connection and two antenna. Credit for monument sign lights not used $745.00 
Total for this Change Order - $29,430.56 or 1.32% of contract 
Total Change Orders for the Project - $33,052.50 or 1.49% of contract 
Purchasing Department Action
FYI notification to Commissioners Court of Contract Change Order No. 3 to M-Pak Construction, Inc. for Construction, New Office Building for Precinct 2 Justice of the Peace & Constable, IFB 2020-272 per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg   
 
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $29,430.56 for Change Order No. 3 to IFB 2020-272, Construction, New Office Building for JP Precinct 2 Justice of the Peace & Constable with M-Pak Construction, Inc. New Contract total is $2,248,052.50. 2018 Tax Notes (4406).
Auditor's Office Action
Tax Note funds available.
Commissioners Court
Change Order No. 3 to Construction, New Office Building for Precinct 2 Justice of the Peace & Constable (IFB No. 2020-272) with M-Pak Construction, Inc. to make various changes to the contract, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $29,430.56
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: FI18LAVNCH-4406-400308043-809110
Fund Transfers
Remarks:
Attachments
Memo
PCOs
Change Order 3