Meeting Date: 03/28/2022  
Amendment No. 1, Brinkley Sargent Wiginton Architects, Adult Detention Addition
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
Request Commissioners' Court consideration and approval of Amendment No. 1 to Brinkley Sargent Wiginton Architects Contract RFQ 2021-353 for:
Phase Two Cost Estimating of the Collin County Detention Center in the amount of $55,500.00. Added because we had to change from Construction Manager at Risk format back to a hard bid format.
Phase Two Additional Civil Engineering Services in the amount of $9,000.00. We expanded the area to include a parking area north of the construction site.
Adult Detention Center Design Services to continue with a portion of the Master-Plan-defined, Phase 3 renovations design services in the amount of $210,195.00 to demo and renovate the current clinic/infirmary area into a new 24-bed skilled nursing area.  This is one of the planned renovation areas that we need to design now, due to its proximity to the Medical/Mental Health building we are currently designing.
Total amount of this change order is $274,695.00 or 0.04% of contract. 
Total Change Orders for this Project - $274,695.00 or 0.04% of contract.
 
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Contract Amendment No. 1 to Brinkley Sargent Wiginton Architects, Inc. for RFQ 2021-353, Professional Services, Architectural, Adult Detention Center Expansion, Phase 2 & 3 per the attached documents. Further authorize the Purchasing Agent to execute the contract amendment. jdg
 
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $274,695 for Amendment No, 1 to RFQ 2021-353, Professional Services, Architectural, Adult Detention Center Expansion, Phase 2 & 3 in the American Rescue Plan Act funds (2132).
Auditor's Office Action
Funds available in Fund 2132, Project code GTARPADC.
Commissioners Court
No. 1 to Professional Services, Architectural, Adult Detention Center Expansion, Phase 2 & 3 (RFQ No. 2021-353) with Brinkley Sargent Wiginton Architects, Inc. to make various changes to the contract, and further authorize the Purchasing Agent to finalize and execute same, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $274,695.00
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: GTARPADC-2132-040010059-809508
Fund Transfers
Remarks:
Attachments
Court Order 2022-283-03-28
Memo
BSW P2 Cost Est Proposal
BSW P2 Civil Eng Proposal
BSW P3 Nursing Renov Proposal
Form 1295
2252 Certification
Contract Amendment 1

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved