Print Back to Calendar Return
AI- 53975
Commissioners Court
Meeting Date: 06/05/2023  
No.5 with Mario Sinacola & Sons Excavating, Inc.for the Outer Loop Access Road Project
Submitted For: Clarence Daugherty Submitted By: Dawn Redwine
Department: Engineering  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
 Collin County Outer Loop from Preston Road (SH 289) to Custer Road (FM 2478) has been completed and a final change order is needed to reconcile the quantities that were actually used compared to those that were estimated in the original contract. Attached is a letter from our design and construction management engineering consulting firm, Jacobs Engineering, which lists additions to the project, revised quantities of bid items and the project quantities that underran and overran. The net amount is an increase of $438,111.59.
 
The contractor met the substantial completion time requirements of the contract and the road was open to traffic on October 2022. Additional signage was added after the road was open to the public and a correction to plan quantities for hot mix asphalt and concrete pavement was needed. The Engineering staff agrees with Jacob’s recommendation of Change Order No. 5 to reconcile the quantities.
 
Funds are available in RI18OL002, however we would like to sweep the funds ($259,847.59) from RI07095 to cover a portion of the change order.  A BA is needed to move 07 funds to 18 funds and new project codes will be created.
 
Recommended Action:  It is requested that the Commissioners Court
-approve Change Order No. 5, increasing the Outer Loop Access Road Project (Limits from Preston Road (SH 289) to Custer Road (FM 2478) contract by $438,111.59, for a final total of $13,800,156.36.
 
-authorize the auditor to transfer
$37,218.74 from RI07095-4206-750300013-809280 to RI0718OL02-4206-750300013-809280
$209,998.29 from RI07095-4210-750300013-80928 to RI0718OL02-4210-750300013-809280
$12,630.56 from RI07095-4211-750300013-80928 to RI0718OL02-4211-750300013-809280

 
Purchasing Department Action
Request Commissioners Court consideration any action regarding approval of change order No. 5 to the contract with Mario Sinacola & Sons Excavating, Inc., IFB 2020-258, Construction, Road, Collin County Outer Loop from East of SH 289 to FM 2478, to reconcile the over runs and under runs of the finished project for the amount of $438,111.59 and a final contract amount of $13,800,156.36. Further, authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Request approval for Change Order No. 5 in the amount of $438,11.59 to IFB-2020-258, Construction, Road, Collin County Outer Loop from East of SH 289 to FM 2478 with Mario Sinacola & Sons Excavating, Inc. Budget Adjustment included in the amount of $259,847.59. New contract total is $13,800,156.36. 2007 & 2018 Bond Funds.
Auditor's Office Action
Funds available in the 2007 & 2018 Bond Funds.  Budget amendment will be processed upon approval.
Commissioners Court
No. 5 to Construction, Road: Collin County Outer Loop from East of SH 289 to FM 2478 (IFB No., 2020-258) with Mario Sinacola & Sons Excavating, Inc. to reconcile the over runs and under runs of the finished projects, and further authorize the Purchasing Agent to finalize and execute same, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 438,111.59
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL002-4024-750300013-809280
2: RI0718OL02-4210-750300013-809280
3: RI0718OL02-4206-750300013-809280
4: RI0718OL02-4211-750300013-809280
Fund Transfers
Remarks:
FY 2023 Budget Adjustment Totaling $259,847.59.
Attachments
Court Order 2023-448-06-05
Memo
Change Order No. 5
Form 1295
2252 Certification
Journal Proof

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved