Interlocal Agreement with NTMWD concerning Right of way for Park Blvd.
Submitted By: Tracy Homfeld
Department: Engineering  
Request Type: CONSENT Agenda Area: Agreement

Information
Department Action
Collin County is in the process of acquiring right-of-way for the extension of Park Boulevard between F.M. Highway 2514 (Parker Road) and State Highway 78.
 
The roadway alignment crosses NTMWD’s main treatment facility tract in Wylie. The County will need to acquire right of way as well as a temporary construction easements and permanent drainage easements.  
 
The attached Park Blvd. Land Acquisition Table outlines the needed ROW (Ex. A), Temporary construction easements (Ex, B), and drainage easements (Ex. C) as well as ROW that was previously acquired for Park Blvd. that the county no longer needs (Ex. E) “Prior Right-of-Way Alignment”.  The property and easements to be acquired were appraised at $291,788.00. The ROW that is to be abandoned was taken into consideration into the overall acreage and appraisal costs.  
 
The NTMWD is designing the McKinney Delivery Point No. 3  and No. 4 pipeline in which the district will need easements from the county (Ex. D). This easement was appraised at $80,888.00.
 
In order to facilitate both projects, we have included the land transactions in this ILA and The total payment to NTMWD shall be $291,788-$80,888 = $210,900 being the difference in the ROW costs for Park Blvd. and the easement cost for the McKinney Delivery Point 3 and 4 pipeline.
 
ACTION:
We request consideration of the attached ILA with NTMWD concerning the construction of Park Blvd. extension and further authorize Judge Hill to execute the ILA and any documents related to the land transactions.
 
We will be available to answer any questions you might have regarding this matter.
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of Interlocal Agreement with North Texas Municipal Water District (NTMWD) for Right of Way acquisition for extension of Park Blvd between FM Highway 2514 and State Hight 78 and authorize County Judge to execute same. sh
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $210,900 for an Interlocal Agreement with North Texas Municipal Water District for Right of Way acquisition for extension of Park Blvd between FM Highway 2514 and State Highway 78. 2018 Bond Fund (4216).
Auditor's Office Action
Bond funds available.
Commissioners Court
Interlocal Agreement with North Texas Municipal Water District for Right-of-Way acquisition for extension of Park Blvd. between FM 2514 and State Highway 78, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 210,900
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18004CO-4216-750300013-809682