Print Back to Calendar Return
AI- 42087
Commissioners Court
Meeting Date: 09/12/2016  
Advertise: Public Works Weston Barn - Metal Roof Replacement
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: CONSENT Agenda Area: Advertisement

Information
Department Action
Request Commissioners’ Court consideration and approval to advertise for bid: Public Works Weston Barn - Metal Roof Replacement – Bid No. 2016-322. This is an approved FY15 Permanent Improvement Project. Estimated cost $12,500.00. 
Purchasing Department Action
Request Commissioners' Court consideration and any action regarding approval of specifications for IFB 2016-322, Public Works Weston Barn Metal Roof Replacement and advertise for same. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available for IFB 2016-322, Public Works Weston Barn: Metal Roof Replacement in the Permanent Improvement Fund (499).
Auditor's Office Action
Funds available in the Permanent Improvement Fund.
Commissioners Court
Public Works Weston Barn Metal Roof Replacement (IFB No. 2016-322), Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: 20,500.00
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: 499-4107-561.75-40
Fund Transfers
Remarks:
 Replace Metal Roof - estimate $12,500.00
Attachments
Court Order
Memo
Bid Packet