ILa with City of Melissa for Fannin Rd from SH 121 to Approx. 2,300 feet S. of Melissa Rd. - 2007 Bond project #07-052
Submitted By: Tracy Homfeld
Department: Engineering  
Request Type: CONSENT Agenda Area: Agreement

Information
Department Action

The Project includes Design, ROW acquisition, and construction for an ultimate 6-lane divided roadway from US 75 to Fannin Rd. The city will only build half the roadway at this time. The project is estimated at $3,000,000.

The County’s 50% participation, or $1,500,000, would come from the City’s 2007 Bond Project #07-052.

ACTION:
We request Commissioners Court consider approval of the Interlocal Agreement between Collin County and the City of Melissa for the Design and Construction of Fannin Rd. from SH 121 (Sam Rayburn Freeway) to Approx. 2,300 feet south of Melissa Rd., 2007 Bond Project #07-052, and authorize Judge Keith Self to sign the ILA.
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of the Interlocal Agreement between Collin County and the City of Melissa concerning the design and construction of Fannin Rd. from SH 121 (Sam Rayburn Freeway) to Approx. 2,300 feet south of Melissa Rd., 2007 Bond Project #07-052;  further authorize the County Judge to execute same. md 

Collin County's participation is a NTE $1,500,000.00.
HR and/or IT Action
Budget Department Action
Budgeted funds available in the City of Melissa Bond Project 07-052 for design and construction of Fannin Rd from SH 121 to approx. 2,300 feet south of Melissa Rd. Total estimated project cost is $3,000,000 with a 50% participation of $1,500,000 from Collin County. Bond Fund (471).
Auditor's Office Action
Bond funds available.
Commissioners Court
Interlocal Agreement with the City of Melissa for the design and construction of Fannin Road from SH 121 (Sam Rayburn Freeway) to approximately 2,300 feet south of Melissa Road (Bond Project No. 07-052).  County participation NTE $1,500,000, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $1,500,000
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: 471-7530-680.92-80 / 07-052
Fund Transfers
Remarks:
Attachments