Print Back to Calendar Return
AI- 42889
Commissioners Court
Meeting Date: 03/27/2017  
Interlocal Agreement with City of Plano for Windhaven Parkway from City Limits to Spring Creek Pkway; 2003 Bond Project 03-065
Submitted By: Tracy Homfeld
Department: Engineering  
Request Type: CONSENT Agenda Area: Agreement

Information
Department Action
The City of Plano has completed the widening for Windhaven parkway from the western city limits to Spring Creek Parkway. The project widened the roadway to 4-lanes from Spring Creek Parkway to Parkwood Blvd. and to 6-lanes from Parkwood Blvd. to the western city limits.

The City has indicated that the final cost of the project is $4.8 M. The 2007 Collin County Bond program allocated $1.6 Million to this project. The attached ILA would commit $1.1M, leaving $500,000 to be reallocated.



ACTION:
We request Commissioners Court consider approval of the Interlocal Agreement with the City of Plano for the widening of Windhaven Parkway from City Limits to Spring Creek Parkway; 2003 Bond Project #03-065; Plano CIP #5741. Collin County participation $1,100,000 and authorize Judge Keith Self to sign the ILA.

Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of the Interlocal Agreement between Collin County and the City of Plano concerning the design and construction of Windhaven Parkway from City Limits to Spring Creek Parkway, 2003 Bond Project #03-065, Plano CIP #5741; further authorize the County Judge to execute same. md

Collin County's participation is a NTE $1,100,000.00.
HR and/or IT Action
Budget Department Action
Interlocal Agreement with the City of Plano for project 03-065 for the widening of Windhaven Parkway from the City Limits to Spring Creek Parkway. Budgeted funds available totals $1,600,000. Collin County participation not to exceed $1,100,000. Remaining $500,000 allocated is to be used towards other City of Plano bond projects. Bond Fund (430)
Auditor's Office Action

Bond funds available.

Commissioners Court
Interlocal Agreement with the City of Plano for the design and construction of Windhaven Parkway from the western city limits to Spring Creek Parkway (Bond Project No. 03-065).  County participation NTE $1,100,000, Engineering.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $1,100,000
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: 430-7530-680.92-80 / 03-065
Fund Transfers
Remarks:
Attachments
Court Order
Memo
ILA
Location Map