Print Back to Calendar Return
AI- 44366
Commissioners Court
Meeting Date: 02/12/2018  
Contract Amendment #1: Dallas North Tollway, Phase 4 Westerly South bound Service Road (Agr 2016-181)
Submitted For: Jeff Durham Submitted By: Teresa Nelson
Department: Special Projects  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
The Engineering Department requests that the contract with Halff Associates Inc. for services relating to the DNT westerly (south bound) service road be increased by $695,000.

The bulk ($655,000) of this increase is for construction phase services which will provide part time construction inspection and construction administration support, with the balance ($39,290) requested for design modifications that would accommodate construction of a pedestrian sidewalk adjacent to the bridge across Doe Branch.

The City of Celina has requested that a sidewalk be included as part of the construction of the bridge over Doe Brach since there will be no development adjacent to the bridge to pay for a sidewalk. In return, Celina has offered to assume maintenance of the Collin County Outer Loop service roads constructed within their jurisdiction.
Purchasing Department Action
Request Commissioners' Court consideration and any action regarding approval of contract amendment No. 1 to the contract with Halff Associates, Inc., for the Design of the Dallas North Tollway South Bound Service Road from US 380 to FM 428, AGR 2016-181, to 1.) add utility relocation assistance, NTTA coordination, and construction inspection and administration services per the attached documentation for the amount of $655,000.00 and 2.)  design modifications to accommodate construction of a pedestrian sidewalk adjacent to the bridge across Doe Branch per the attached documentation for the amount of $39,290.00. Further authorize the Purchasing Agent to execute the contract amendment. md

Halff Associates, Inc. was awarded the design of the project per CO# 2016-162-03-07. md
HR and/or IT Action
Budget Department Action
Budgeted funds available for Contract Amendment No. 1 with Halff Associates Inc. in the amount of $694,290.  Amendment includes $655,000 for construction phase services and $39,290 for design modifications.  General Fund (001).
Auditor's Office Action
Commissioners Court
No. 1 for the Design of the Dallas North Tollway South Bound Service Road from US 380 to FM 428 (AGR No. 2016-181) with Halff Associates, Inc. to make various changes to the contract, budget amendment in the amount of $694,290 for same and further authorize the Purchasing Agent to finalize and execute same, Special Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $694,290
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: 001-7530-680.92-50 / 070050
Fund Transfers
Trans Amt: $694,290 From: 001-7530-680.96-82 / 070050 To: 001-7530-680.92-50 / 070050
Dept. Name: Additional Line Items:
Remarks:
This item contains two different changes to contract. One totaling $655,000 (construction inspection), and the other $39,290 (design modification).  Should the court determine to only have an increase for construction inspection, then that total dollar amount will be all that's necessary to reallocate.  Just wanted to provide heads-up for this item.
Attachments
Court Order
Department Memo
Amendment No. 2
Scope of Svcs_Const. Inspection
Fee Schedule_Const Inspection
Scope of Svcs_Bridge Modification
Fee Schedule_Bridge Modification
Form 1295
2252 Certification
2270 Verification

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved