FYI - Change Order No. 2 - Collin County Adventure Camp Trail Rehabilitation - Denco Construction Specialists
Submitted For:
Bill Burke
Submitted By:
Lisa Bunch
Department:
Construction Projects
Request Type:
FYI
Agenda Area:
Miscellaneous
Information
Department Action
FYI to Commissioners' Court for change order No. 2 to Denco Construction Specialists, IFB No. 2017-273, Collin County Adventure Camp Trail Rehabilitation. This change order is to add a total of seventy (70) days to the contract.
Forty-seven days of rain/wet conditions and twenty-three days for material change as approved on change order No. 1.
This change order totals $0.00
Total change orders for the project - $0.00 or 0.00%
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 2 to Denco CS Corp for IFB 2017-273, Construction, Collin County Adventure Camp Trail Rehabilitation to add seventy (70) days to the contract completion date. jdg
HR and/or IT Action
Budget Department Action
Change Order No. 2 to Denco CS Corp for bid 2017-273, Construction, Collin County Adventure Camp Trail Rehabilitation. No budget impact. Bond Fund (4004).
Auditor's Office Action
Bond funds available.
Commissioners Court
Change Order No. 2 to Construction, Collin County Adventure Camp Trail Rehabilitation (IFB No. 2017-273) with Denco CS Corp. to add 70 days to the contract completion date, Construction & Projects.
Budget Information
Information about available funds
Budgeted:
Funds Available:
Adjustment:
Amount Available:
Unbudgeted:
Funds NOT Available:
Amendment:
Account Code(s) for Available Funds
1:
OI01OC-4004-400308001-809101
Fund Transfers
Remarks:
This change order totals $0.00
Attachments
Memo
Contractor Change Order Request
Change Order 2