FYI: Change Order No. 1 - New Camera Installation and Intercom System Upgrade at C.C. Detention Facility - STS360
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for Change Order No. 1, to Sigma Surveillance Inc., DBA STS 360, IFB No. 2018-150, New Camera and Intercom System Upgrade at the Collin County Detention Facility. CO 1 - Owner requested add to install relays and boards in addition to what was shown in the original bid documents. This equipment is needed to complete the remaining two pods to the Techworks system. $12,151.75. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
Total for this Change Order  - $12,151.75 or 16.5% of contract.
Total Change Orders for the Project - $12,151.75 or 16.5% or contract
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 1 to Sigma Surveillance Inc. DBA STS360, IFB 2018-150, New Camera and Intercom System Upgrade at Collin County Detention Facility for owner requested add to provide and install additional intercom hardware. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.  jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $12,151.75 for Change Order No. 1 to IFB 2018-150, New Camera and Intercom System Upgrade at Collin County Detention Facility, with Sigma Surveillance, Inc DBA STS360. (0499)-Permanent Improvement Fund.
Auditor's Office Action
Funds available in the Permanent Improvement Fund.
Commissioners Court
No. 1 to New Camera Installation and Intercom System Upgrade at Collin County Detention Facility (IFB No. 2018-150) with Sigma Surveillance, Inc. DBA STS360 for owner requested add to provide and install additional intercom hardware (previously approved by the County Administrator per Court Order No. 2007-180-02-27), Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: +$12,151.75
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: PAN41003-0499-400108002-809002