FYI Change Order No. 3 - Collin County Adventure Camp Trail Rehabilitation - Denco Construction Specialists
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for Change Order No. 3 to Denco Construction Specialists, IFB No. 2017-273, Collin County Adventure Camp Trail Rehabilitation. Owner and YMCA requested add to use remaining funds for Trail Repair to add culverts and stockpile material for maintaining trails. The Budget for Trail Repair was set per Court Order 2014-864-11-10 to extend the YMCA Management Agreement. Once this change order is completed there will be $3,840.00 remaining in the Budget. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. We request a budget amendment in the amount of $24,415.00 from Program Contingency to Building Improvements for this change order.
Total for this Change Order - $25,011.39  or 5.1% of contract.
Total Change Orders for the Project - $25,011.39 or 5.1% of contract.
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 3 to Denco CS Corp for IFB 2017-273, Construction, Collin County Adventure Camp Trail Rehabilitation for owner requested installation of additional culverts and stockpile material for maintaining trails and to add twenty (20) additional days to the contract completion date. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $25,011.39 for Change Order No. 3 to IFB 2017-273, Construction, Collin County Adventure Camp Trail Rehabilitation.  Budget Adjustment in the amount of $24,415 needed to move funding to appropriate account.  See Project Budget Adjustment attachment for details. Open Space Bond Fund (4004).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 3 to Construction, Collin County Adventure Camp Trail Rehabilitation (IFB No. 2017-273) with Denco CS Corp. for owner requested installation of additional culverts and stockpile material for maintaining trails, add 20 additional days to the contract completion date and budget amendment in the amount of $24,415 for same (previously approved by the County Administrator per Court Order No. 2007-180-02-27), Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $25,011.39
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: OI01OC-4004-400308001-809101
Fund Transfers
Remarks:
FY 2019 Budget Adjustment totaling $24,415.
Attachments
Memo
Contractor Change Order Proposal
Change Order 3
Project Budget Adjustment