Change Order No. 1 - Myers Park Show Barn Electric - KE Industrial
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for change order No. 1 to KE Industrial, IFB No. 2018-326, Construction, Myers Park Show Barn Electrical Upgrade. CO 1- Owner requested add to install additional outlets in the Arena and Concession areas. These outlets were left out of the original base bid due to budget concerns. Now that most of the install is complete these funds can be used to add these outlets. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
Total for this Change Order - $19,498.00 or 24.1 % of contract
Total Change Orders for the Project - $19,498.00 or 24.1 % of contract
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 1 to KE Industrial LLC, IFB 2018-326, Construction, Myers Park Show Barn Electrical Upgrade for owner requested add to install additional outlets in the Show Barn Arena and Concession areas. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Budgeted funds available for Change Order No. 1 to KE Industrial, LLC on IFB 2018-326, Construction, Myers Park Show Barn Electrical Upgrade in the amount of $19,498. Open Space Bond Fund (4016).
Auditor's Office Action
Bond funds available.
Commissioners Court
Change Order No. 1 to Construction, Collin County Myers Park Show Barn Electrical Upgrade (IFB No. 2018-326) with KE Industrial LLC for owner requested add to install additional outlets in the Show Barn Arena and Concession areas (previously approved by the County Administrator per Court Order No. 2007-180-02-27), Construction & Projects.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $19,498.00
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: OI07PG99-4016-750600044-626550
Fund Transfers
Remarks:
 