FYI to Commissioners' Court for Change Order No. 1 to JJ Red Commercial Roofiing for the Justice Center Roof Recovery.
CO 1- Consultant requested add to add liquid flashing to parapet wall in areas that are too low for cap sheet flashing. $9,075.00.
Contractor requested to extend the project completion date by ninety-eight calendar days due to weather and no weekend work allowed from November 3 to March 31. Original project completion date: April 6, 2019. New project completion date: August 21,
2019.
Total for this Change Order - $9,075.00 or 0.42% of contract
Total Change Orders for the Project - $9,075.00 or 0.42% of contract
Thank you
|