Request Commissioners' Court consideration and approval of Change Order No. 2 to JJ Red Commercial Roofing for the Justice Center Roof Recovery.
Item 1. Owner Requested Change Order to credit the remaining allowance for wet roofing material removed. Not all of the allowance was used as determined by daily core sampling during the project. ($106,967.72)
Item 2. Architect requested change to change materials for coping waterproofing. Originally selected material would not adhere to the coping. No Cost
Total for this Change Order – ($106,967.72) or (5.0%) of contract
Total Change Orders for the Project – ($97,892.72) or (4.6%) of contract
|