Print Back to Calendar Return
AI- 47951
Commissioners Court
Meeting Date: 02/10/2020  
P25 Radio System Change Order
Submitted For: Jim Skinner Submitted By: Lawana Downs
Department: Sheriff's Office  
Request Type: CONSENT Agenda Area: Amendment

Information
Department Action
P25 radio system change order #11 which includes
     Generator Inspection at our Princeton and Farmersville Towers - $2,919.90 
     Generator Inspections- PM Time - $1,138.88 
     Replacement parts and labor for damaged equipment from a water leak in the Verona shelter -$2,876.70 
     SUA System Upgrade 2020 - $12,000 (Necessary because of the project delays) 

The total cost of this change order is $18,935.48. The new contract value to $11,477,369.97, making the contract delta $769,588.97. 
Purchasing Department Action
 Request Commissioners' Court consideration and any action regarding approval of Amendment No. 11 to Contract 2016-020, P25 Trunked Radio System Replacement in the amount of $18,935.48 making the new contract amount $11,477,369.97 and authorize Purchasing Agent to execute same. sh
HR and/or IT Action
Budget Department Action
Budgeted funds available in the amount of $18,935.48 for Amendment No. 11 to Contract 2016-020, P25 Trunked Radio System Replacement. New contract total is $11,477,369.97.General Fund (0001).
Auditor's Office Action
Funds available in the General Fund.
Commissioners Court

No. 11 to P25 Trunked Radio Replacement (Contract No. 2016-020) with Motorola Solutions, Inc. to provide various changes to the contract and further authorize the Purchasing Agent to finalize and execute same, Sheriff.


Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $18,935.48
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: BDP10001-0001-100010001-809020
Fund Transfers
Remarks:
Attachments
Court Order
Memo
Amendment No. 11
Motorola Change Order No. 11
2252

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved