Print Back to Calendar Return
AI- 48236
Commissioners Court
Meeting Date: 05/04/2020  
Change Order No 1 to Contract 2019-109; Outer Loop construction between DNT and SH289
Submitted For: Jeff Durham Submitted By: Teresa Nelson
Department: Special Projects  
Request Type: CONSENT Agenda Area: Change Order

Information
Department Action
The Engineering Department requests that the contract with Mario Sinacola & Sons Excavating, Inc. be adjusted to reflect changes in materials and actual quantities utilized for construction.
 
While there are several items listed on this change order, the additional cost is primarily due to the increased amount of Type C1 embankment required in areas with side slopes that are steeper than 4:1.
 
The net contract increase requested is $28,830.75 and we will be available to answer any questions you might have regarding this matter.
 
Purchasing Department Action
Request Commissioners Court consideration and any action regarding approval of change order No. 1 to the contract with Mario Sinacola & Sons Excavating, Inc., IFB 2019-109, Construction, Road, Outer Loop Access Road from Dallas Pkwy. to East of SH 289, to allow for various changes per the attached documentation for an increase of $28,830.75 for a new total contract value of $18,584,846.80. Further authorize the Purchasing Agent to execute same. MD
HR and/or IT Action
Budget Department Action
Approval of Change Order No. 1 to IFB 2019-109, Construction, Road, Outer Loop Access Road from Dallas Pkwy to East of SH 289 with Mario Sinacola & Sons Excavating, Inc. in the amount of $28,830.75 for various changes. New contract total is $18,584,846.80. 2018 Bond Fund (4215).
Auditor's Office Action
Bond funds available.
Commissioners Court
No. 1 to Construction, Road, Outer Loop Access Road from Dallas Pkwy. to East of SH 289 (IFB No. 2019-109) with Mario Sinacola & Sons Excavating, Inc. to make various changes to the contract, and further authorize the Purchasing Agent to finalize and execute same, Special Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available: $28,830.75
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: RI18OL001 4215-750300013-809280
Fund Transfers
Remarks:
Attachments
Court Order
Revised Dept Memo
Engineers Recommendation
Change Order No. 1
2252 Certification
Form 1295

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved