AI- 48475
Commissioners Court
Meeting Date: 06/01/2020  
FYI - Change Order No. 3 - Justice Center, Replacement of Chilled Water Actuators and Valves - Expert Services
Submitted For: Bill Burke Submitted By: Lisa Bunch
Department: Construction Projects  
Request Type: FYI Agenda Area: Miscellaneous

Information
Department Action
FYI to Commissioners' Court for Change Order No.3 to Expert Services for IFB 2019-084, Construction, Collin County Justice Center, Replacement of Chilled Water Actuators and Valves.
PCO 3- Owner requested credit to reverse the majority of Change Order 2 from the scope of work. During demolition of the existing insulation a suspicious substance was found and tested. Work on change order 2 was halted and then determined to have changed significantly due to remediation being needed by a licensed contractor. Some labor and material was used prior to halting the work and only material used was charged to us. ($18,338.80)
Total for this Change Order- ($18,338.80) or 11.78% of contract
Total Change Orders for the Project- $16,911.66 or 10.86% of contract
This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27.
Purchasing Department Action
FYI notification to Commissioners' Court of Contract Change Order No. 3 to Expert Services, LLC for Construction, Collin County Justice Center, Replacement of Chilled Water Actuators and Valves, IFB 2019-084 per the attached documents. This change order was previously approved by the County Administrator per Court Order No. 2007-180-02-27. jdg
HR and/or IT Action
Budget Department Action
Change Order No. 3 to Expert Services, LLC for IFB 2019-084, Construction, Collin County Justice Center, Replacement of Chilled Water Actuators and Valves. Change Order reverses the majority of Change Order No. 2 due to remediation needed by a licensed contractor.  Change Order results in a credit of $18,338.80.  New contract total is $172,653.66. Permanent Improvement Fund (0499).
Auditor's Office Action
Funds available in the Permanent Improvement Fund.
Commissioners Court
Change Order No. 3 to Construction, Collin County Justice Center, Replacement of Chilled Water Actuators and Valves (IFB No. 2019-084) for owner requested deductive change order to reverse the majority of Change Order No. 2 from the scope of work, Construction & Projects. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1: 0499-40010-8002-56-30-0000-637540
Fund Transfers
Remarks:
Credit to account  ($18,338.80)
Attachments
Memo
Change Order 3