Print Back to Calendar Return
AI- 49501
Commissioners Court
Meeting Date: 12/07/2020  
Hills of Lone Star Phase 7B_Northgate: Acceptance of Roads for County Maintenance
Submitted For: Clarence Daugherty Submitted By: Mike Sullivan
Department: Engineering  
Request Type: CONSENT Agenda Area: Miscellaneous

Information
Department Action
The plat for the above-mentioned subdivision was approved by Commissioner’s Court on April 17, 2017. The infrastructure was completed according to county specifications and inspected by the Collin County Engineering and Public Works staff. The infrastructure entered into a 2-year maintenance period on October 2, 2018. The maintenance period is complete and the owner has completed the required repairs as requested by County Engineering and Public Works staff. Once approved, Public Works will include these roads on their maintenance list. The Final Plat is attached to show the sections of roads that are up for maintenance consideration.

We request Commissioner Court consideration of approval to accept the roads within Hills of Lone Star Phase 7B_Northgate for County Maintenance
Purchasing Department Action
No action by Purchasing.
HR and/or IT Action
Budget Department Action
No action by Budget & Finance.
Auditor's Office Action
No action by Auditor.
Commissioners Court
Accept the roads within Hills of Lone Star Phase 7B_Northgate for county maintenance, Engineering. 

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Remarks:
Attachments
Court Order 2020-1191-12-07
memo
map
plat

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved