The Engineering Department requests consideration of the proposed Amendment #3 to the contract with Jacobs Engineering for services relating to the construction of the CCOL from SH 289 east to FM 2478. The contract total will be increased by $725,713.88
The bulk of this increase, $572,443.28, is for construction phase services, including direct expenses, and to provide project construction inspection. The balance, $153,270.60, being for additional engineering construction administrative services in support of construction activities.
Jacob's scope of work and a detailed breakdown of their proposed fees is attached.
ACTION:
Commissioners Courts is requested to approval contract amendment #3 to the Jacobs Engineering Contract #2019-269 in the amount of $725,713.88.
I will be available to answer any questions you might have regarding this matter.
|
Purchasing Department Action |
Request Commissioners Court consideration and any action regarding approval of contract amendment No. 3 to the contract with Jacobs Engineering Group, Inc., AGR 2019-269, Professional Services, Engineering, Preparation of Final Plans, Specifications and Estimates (PS & E) for the Collin County Outer Loop, Segment 3B East of Preston Rd (SH 289) to Custer Rd (FM 2478), to add construction phase services, construction inspection services and construction administration services for the amount of $725,713.88 for a new total contract amount of $1,605,656.16. Further, authorize the Purchasing Agent of execute same. MD |
HR and/or IT Action |
|
Budget Department Action |
Budgeted funds available in the amount of $725,713.88 for Contract Amendment No. 3 with Jacobs Engineering Group Inc for AGR 2019-269, Professional Services, Engineering, Preparation of Final Plans, Specifications and Estimates for the Collin County Outer Loop, Segment 3B East of Preston Rd to Custer Rd to add construction phase services, construction inspection services and construction administration services. The new contract total is $1,605,656.16. |
Auditor's Office Action |
Tax Note funds available. |
Commissioners Court |
No. 3 to Professional Services, Engineering, Preparation of Final Plans, Specifications and Estimates for the Collin County Outer Loop, Segment 3B East of Preston Road (SH 289) to Custer Road (FM 2478) (Contract No. 2019-269) with Jacobs Engineering Group Inc., to add construction phase services, construction inspection services, and construction administration services, and further authorize the Purchasing Agent to finalize and execute same, Engineering. |
|
Budget Information |
Information about available funds |
Budgeted: |
Funds Available: |
Adjustment: |
Amount Available: |
$725,713.88 |